Technical Snapshot
| Client | Betrimex Import Export Joint Stock Corporation (BETRIMEX), Vietnam |
| Project Year | 2023 |
| Solution Supplied | Complete Coconut Processing Line |
| Feed Capacity | ~2267 kg/hr @ 57% moisture |
| Output Capacity | ~1000 kg/hr dried product |
| Final Moisture | ~2.5% |
| Evaporation Load | ~1267 kg/hr |
| Installed Load | ~241.5 HP |
| Steam Consumption | ~3000 kg/hr |
| Control System | Automated PLC-controlled operations |
Project Overview
- Scope included design, engineering, manufacturing, supply, and commissioning of a fully integrated, high-capacity drying and processing system tailored for desiccated coconut production.
The Challenge
- BETRIMEX required a solution capable of handling high-throughput coconut processing.
- The plant needed consistent product quality across multiple grades of desiccated coconut.
- Moisture levels had to be tightly controlled to meet international quality standards.
- The client also required robust, continuous industrial performance for large-scale operations.
The Solution
- Gem Drytech supplied a comprehensive coconut processing system engineered for continuous and hygienic food-grade production.
- Core equipment supplied included: Power Grinder Feeding Screw Conveyor, Power Grinder with Agitator, Desiccated Coconut Cutter, Discharge Screw Conveyor, Blancher with Steam Locking Arrangement, Multi-Stage Combination Fluid Bed Dryer System, Steam Radiator & Steam Control System, Tray Type Belt Cooler, Vibratory Inspection Table, Inclined Screw Conveyors, Vibro Sifter, and Central Control Panel (SS 304).
- The system was built with stainless steel construction and automated PLC-based control for reliable, food-grade operation.
Performance & Acceptance Criteria
- Output Capacity achieved as per defined acceptance conditions: High Fat – 1000 kg/hr; Medium Fat – 900 kg/hr.
- Product quality met international standards including BTM / STPS / TC standards.
- System efficiency for medium-grade production was defined at 60–65%.
- Operational parameters included installed load of about 241.5 HP and steam consumption of about 3000 kg/hr.
Execution Timeline
- Manufacturing: ~150 days.
- Shipping: ~21 days.
- Installation: 40–60 days.
- Commissioning: 7–10 days.
Project Validation
- The client formally confirmed that the equipment was delivered, installed, and fully operational.
- The system met all contractual and performance requirements.
- Final acceptance was granted after successful commissioning.
Business Impact for BETRIMEX
- Scalable, high-capacity production capability.
- Consistent product quality across multiple coconut grades.
- Reliable and efficient drying performance.
- Optimized operational and energy efficiency.
What This Demonstrates
- This project showcases Gem Drytech’s ability to deliver large-scale, integrated processing systems.
- It highlights Gem Drytech’s capability to execute international turnkey projects.
- It demonstrates precision drying with measurable performance outcomes.
Applicability
- Relevant for desiccated coconut, coconut flakes, copra, grated coconut, and other high-capacity food drying applications where hygiene, consistency, and moisture control are critical.
Suggested Image Use
- Complete coconut processing line or plant installation view.
- Multi-stage dryer image.
- Desiccated coconut product photo.
- Commissioning or operating plant shot if available.